Tuesday, September 28, 2010

Construction Ends


It is wonderful how long it takes to get something done.
You know what this house needs – a Front Porch. Dec 2008
Let us see - call architect on March 2009.
Design received back in April 2009. Architect paid $$
Engineers go to work May 2009. Engineers paid $
Send project out for bids August 2009.
Pick contractor give deposit September 2009. $$$
November 2009 city rejects permits due to set back zoning rules.
File an appeal with Board of Adjustment Jan 2010. $
Appeal process involves public notice and hearing – Board postpones due to lack of quorum.
Board meets votes to approve porch May 2010
Planning department must wait 30 days to issue approval letter June 2010
Building department says planning department doesn’t have info??
Permits issued June 2010, contractor tied-up with major job will have to wait.
Construction begins August 2010. $$$
Construction ends September 2010 $$$
Homeowner finishing work to begin, sanding, painting, planting flowers around the area, buying furniture for the porch, etc – so maybe by December 2010.
For pictures go to: http://www.facebook.com/album.php?aid=231630&id=617928368&l=4f28adb37a